Monday
afternoon (~1pm) the gravel arrived to set the base of our slab. Matt
had to work until later in the afternoon so it was Bethy operating the
tractor and starting to spread the gravel. To help keep the dust down
we obviously planned on doing it on a rainy day (hahahahaha noooot); the
rain was consistent but not heavy, so the work continued.
Bethy moving the gravel! |
Al
was working on the sewer pipe layout that would be installed under the
slab. The toilet flange, utility room drain, and bathroom shower drain
all needed to be glued up and buried in a trench before we laid gravel
and poured the slab. Bob showed up and helped with digging for the sewer
pipes and spreading the gravel. Just before the final truck load of
gravel showed up, Matt arrived and took over tractor duties so that
Bethy could get back to work.
Matt takes a turn on the tractor |
Josh
arrived shortly thereafter and helped dig for the sewer pipes as well.
As Matt continued spreading and starting to get an even edge, the pipe
was being glued up by Al, and the majority of the trench for the sewer
pipe was dug by Josh and Bob.
A clean pipe is a happy pipe |
However,
as we were just starting to see real progress, the skies opened up and
the rain became so heavy that we had to call it for now. We waited in
our cars for a short while, but when the rain hadn't stopped we called
it a day.
About how we left the site the first day |
Tuesday afternoon, with a relatively dry forecast, Matt and Al got back to work. Matt continued spreading gravel and starting to achieve final grade with the help of some string lines and a level on a stick.
Not too level yet, but we're getting there. |
North wall waste lines |
Nice Pipes!! |
Once
we got the OK from the inspector we began to bury the pipes under dirt,
taking care to tamp down in small layers. We then got out the
compactor which we borrowed from Matt's uncle Ace (Thanks, Ace!!). We
got it up and running and tested it out to see how much compaction we
would get and thus what level we really wanted to be at before running
it.
Testing out the compactor. |
Updated budget:
+ $320.09 for various plumbing supplies
+ $988.20 for 3 trucks of #1 gravel, 14 yds each
TOTAL SPENT SO FAR: $46,638.80
No comments:
Post a Comment