Thanks to the ridiculous amount of rain we've gotten
right after we got our building permit,
we have been very slow to get started and have been put about two weeks
behind our desired schedule at this point. Thankfully we finally had
some decent enough weather over the past few days to make some progress.
On Sunday the 16th, the weather broke mid-way in the afternoon and we were able to hang some strings along our
leveled plane.
We used kite string for this purpose, as it was fine enough not to sag
too much under its own weight but strong enough that it could be pulled
tightly. We added 2 inches in each direction (so, overall dimensions of
36'x68') so that when we dig the footer trenches there is space for 2"
insulating foam and 2" wooden forms around the perimeter of where the
house will be sitting (as these materials are not structural and
therefore should not bear any load). We then spray painted over the
string to create outside lines to dig the trenches along.
After this, we prepped the
rigid insulating foam
for installation. The boards started out as 2"x4'x8', which was twice
as wide as we needed, so we used the scoring on each board to split them
in half to 2' wide. The engineering drawings stated that the foam was
sealed in plastic, so we purchased a roll of black plastic sheeting and
wrapped each of the 24 boards like they were presents.
On
Monday the 17th we got the tractor to the site and started trenching at
the North-West corner of the house. You can see the 5 pictures below.
Digging was pretty easy as long as the centerline of the tractor was
lined up with the trench line. Problems started to arise within the
first 30 minutes, the water level in the bottom of the trench was
increasing. We got most of the way along the back wall and then decided
to stop for the day, because we were having some issues with dirt
slumping back in the hole. We tried to bail some water out but it
definitely was coming into the trench. All told it did not take that
long (~3hrs) but with the wet ground and water issues we decided to
level the bottom and hold off until another day.
|
The Trench Begins |
|
|
We have to go down 3ft and luckily the shovel reaches |
|
Bucket of Dirt |
|
Hmmmm it may be a little wet |
|
Yep, definitely wet, this is what we got done for the day |
So we skipped Tuesday and went to work..... :/ Our
friendly foreman Al (Bethy's Dad) went to the trench and bailed water
out. It seemed to not be too deep (3-4" at most) but also didn't seem
to really be subsiding either. Hopefully it will dry out before we fill
it with concrete.
On Wednesday the 19th we decided it
was dry enough and hot enough to continue the trench. we got to the
North-East corner which also necessitated our first attempt to get the
tractor over the trench (and hopefully not ruin the trench or end up
with a tractor in there either!). It was a little hairy at times but
ultimately successful on both counts. So we rounded the corner and
kept going.
|
Some slumping evident from Monday |
|
Our First Corner!!! |
|
And what a nice Corner it is!!! |
About halfway through the day we got a random visit
from our friendly Town Building Inspector Gerry. He was glad to see us
all hard at work with no slacking going on. We showed him a bit of our
continuous water problem but he actually said that it looked fine and
that if it were a foot or more of water he would be worried, but 2 or 3
inches is nothing to worry about (cue sighs of relief). So on we went
and got close to the end before we finally called it a day with just a
few more feet on the west side to go.
No comments:
Post a Comment